Guidelines of Solar Photovoltaic Installation on Net Energy Metering (NEM) Scheme

 

Description Version Download
Guideline For Solar Photovoltaic Installation Under The Programme Of NEM Rakyat And NEM GoMEn In Peninsular Malaysia UPDATED as of 20 September 2024
Net Energy Metering (NEM) Contract for NEM Rakyat UPDATED as of 8 March 2021
Net Energy Metering (NEM) Contract for NEM GoMEn UPDATED as of 8 March 2021

PROCEDURE FOR NET ENERGY METERING ASSESSMENT STUDY (NEMAS)

Before applying for the NEM application, the interested party is required to contact the Distribution Licensee (TNB) to conduct NEM Assessment Study (NEMAS) for installation above 72 kW. The requirement for a mandatory study is generally based on the rated kW of the proposed installation as shown table below :

Installed CapacityStudy RequiredFee of Study
1-72 kWNo-
>72 kW - 180 kWYesRM1,000.00
>180 kW - 425 kWYesRM5,000.00
>425 kW - 1 MWYesRM8,000.00

The studies shall be conducted by the DL or its appointed consultant to establish the technical and safety requirements and determine the feasibility of the connection.

DescriptionVersionDownload
NEMAS Process FlowNEW as of 2 October 2019
NEM - Technical Study Application FormNEW as of 2 July 2018
Icon
126.23 KB
13319 Downloads
NEM Customer Load Profile FormNEW as of 2 July 2018
List of TNB Nodal PointsNEW as of 14 April 2020
List of Qualified ConsultantsUPDATED as of 1 April 2024

PROCEDURE FOR NEM METER APPLICATION AND SIGNING NEM CONTRACT

  • Please click the Flowchart of NEM Meter Application Process  for the details on workflow.
  • NEM applicant must submit the application, only after all of the installation work for Solar PV fully completed.
  • Please ensure that meter requirement is fulfilled according to TNB’s Electricity Supply Application Handbook (ESAH) obtainable from TNB’s website, prior submitting the application.
  • Kindly update the customer’s email address in NEM Meter Application Form and NEM Declaration Form in order to ensure delivery of demand letter, NEM Welcome Letter and NEM bill.
  • Only fully-completed application will be processed. Incomplete application will be returned to applicant. TNB reserves the right to reject incomplete submission.
  • Submission must be done at TNB Subzone Office, including the following forms and supporting documents:

Net Energy Metering (NEM) Meter Application with all of the forms and supporting documents as below :-

  • NEM Meter Application Form
  • NEM Certificate
  • Pictures of TNB meter and interconnection from the grid;
  • Picture of proposed meter location (If there are changes of meter location for the existing meter)

NEM Contract including the following forms and supporting documents as below:-

  • NEM Declaration Form (TNB Contract)
  • Form G & Form H
  • A copy of Generating License by Suruhanjaya Tenaga (subject to requirement according to Electricity Supply Act 1990)
  • NEM Contract (Domestic/Non Domestic)
  • TNB Inspection & Commissioning Form
DescriptionVersionDownload
NEM Meter Application FormUPDATED as of 27 July 2020
Icon
464.12 KB
16655 Downloads
NEM Rakyat & NEM GoMEn Application Form (TNB Contract) UPDATED as of 13 July 2021
TNB Inspection & Commissioning FormNEW as of 2 July 2018
Icon
147.71 KB
11413 Downloads

For any enquiries, please contact :

Puan Sunarni binti Maulan

 

Telephone : 03-7967 9222
Email : [email protected] / [email protected]

 

Lead (Green Energy Management)
Level 4, Tower D, TNB Platinum,
No 3, Jalan Bukit Pantai, Bangsar,
59100 Kuala Lumpur.