Before applying for the FiT application, the interested party is required to contact the Distribution Licensee (DL)
for the below study:
- Power Systems Study (PSS) for any RE installation more than 425 kW and above; or
- Connection Confirmation Check (CCC) for any RE installation more than 12 kW up to 425 kW.
For grid-connection, PSS or CCC are necessary to assess the potential impact of the distributed generation on the planning and operation of the DL’s distribution system. The studies shall be conducted by the DL or its appointed consultant.
For any enquiries on PSS, please contact :
- Tenaga Nasional Berhad (TNB)
Ir. Kartina binti Hasim
019 – 651 5962
email: [email protected]
Lead (Green Energy Management),
Retail Division,
Tenaga Nasional Berhad (TNB),
Level 4, Tower D, TNB Platinum,
No 3, Jalan Bukit Pantai, Bangsar,
59100 Kuala Lumpur.
- Sabah Electricity Sdn. Bhd. (SESB)
Mr. Terrence John Kouju
088 – 282 478
email [email protected]
Chief Engineer
Sustainable Energy Development,
Asset Development,
6th Floor, Wisma SESB,
Jalan Tunku Abdul Rahman,
88673 Kota Kinabalu,
Sabah, Malaysia.
Connection Confirmation Check :
Net Export Capacity or Rated kWp of RE Installation | Cost (RM) | Completion Period |
More than 12kW up to 180kW | 1,000 | 30 Days |
More than 180kW up to 425kW | 5,000 | 30 Days |
Power Systems Studies (PSS) Cost and Completion Period :
No. | Net Export Capacity or Rated kWp of RE Installation | Cost (RM) | Completion Period |
01. | Above 425kW & up to & including 1MW or above 425kWp and up to and including 1000kWp | 20,000 per installation | 30 Days |
02. | Above 1MW & up to and including 10MW or 1,000kWp and up to and including 10, 000kWp | 40,000 per installation | 40 Days |
03. | Above 10MW & up to and including 30MW or 10, 000kWp and up to and including 30,000kWp | 60,000 per installation | 50 Days |
04. | Above 425kW and up to and including 1MW or above 425kWp and up to and including 1,000kWp for housing development or individual applications on the solar PV to be connected to the same distribution substation. | 500.00 per installation | 60 Days |