|
Before applying for the FiT application, the interested party is required to contact the Distribution Licensee (DL) for the below study:
i. Power Systems Study (PSS) for any RE installation of 180 kW and above; or
ii. Connection Confirmation Check (CCC) for any RE installation exceeding 72 kW up to and including 180 kW.
For grid-connection, PSS or CCC are necessary to assess the potential impact of the distributed generation on the planning and operation of the DL’s distribution system. The studies shall be conducted by the DL or its appointed consultant.
For any enquiries on PSS, please contact Dr. Ahmad Jaafar Abdul Hamid at 03-7967 9377 or email RE@tnb.com.my
Head (Renewable Energy & Green Technology)
Customer Service and Metering Dept,
TNB Distribution,
16th Floor, Wisma TNB,
No.19, Jln Timur, Petaling Jaya,
Selangor Darul Ehsan,
Malaysia.
Power Systems Studies (PSS) Cost and Completion Period:
|
Net Export Capacity or Rated kWp of RE Installation |
Cost (RM) |
Completion Period |
|
Up To 1 MW |
20,000 |
30 Days |
|
More Than 1 MW Up To 10 MW |
40,000 |
30 Days |
|
More Than 10 MW Up To 30 MW |
60,000 |
42 Days |
|
Additional For Insulation Coordination Studies If Required |
20,000 |
10 Days |
|
Additional for Solar PV - Dynamic Study (Voltage Fluctuations) If Required |
10,000 |
- |
Connection Confirmation Check (CCC) Cost and Completion Period: RM 1,000 within 21 Days of receipt of such request.
|